FixVault

Installation Procedure

    Fig 1: Generator
    GM1669928Courtesy of GENERAL MOTORS CORP.
  1. Position the generator to the engine.
  2. Install the generator bolts finger tight in the following sequence.
    1. Upper bolt
    2. Side bolt
    3. Lower bolt
  3. NOTE: Refer to Fastener Notice in Cautions and Notices.
  4. Tighten the generator bolts.

    Tighten:  Tighten the bolts to 50 N.m (37 lb ft).

  5. Fig 2: Generator Terminals
    GM1670187Courtesy of GENERAL MOTORS CORP.
  6. Install the starter solenoid cable terminal (3) to the generator.
  7. Install the generator terminal nut (2).

    Tighten:  Tighten the nut to 12 N.m (106 lb in).

  8. Position the starter solenoid cable protective boot (1) at the generator.
  9. Fig 3: Engine Wiring Harness Electrical Connector From Generator
    GM1663951Courtesy of GENERAL MOTORS CORP.
  10. Connect the engine wiring harness electrical connector (5) to the generator.
  11. Install the drive belt. Refer to Drive Belt Replacement .
  12. Install the radiator. Refer to Radiator Replacement .
  13. Connect the negative battery cable. Refer to Battery Negative Cable Disconnect/Connect Procedure .