FixVault

Dynamic Test

    IMPORTANT: Do not allow the solenoid to be energized for more than 2 seconds.
  1. Install fused jumper wire between the high control terminal 1 and 12 volts. Install a jumper wire between the low reference terminal 2 and momentarily connect to ground.
  2. Point the CMP actuator solenoid towards a shop towel. Observe the operation of the solenoid immediately extends.
    • If the function does not perform as specified, replace the CMP actuator solenoid.