FixVault

Starter Assembly: Remove, Install, and Overhaul

WARNING: This page is about the E Class 2.2 D, which is a different variant/trim than selected.
Includes: Turn Commutator, test Armature and Fields, replace Brushes, Bearings and Solenoid (where applicable).

Applies ToNoteStandard HoursWarranty HoursSkill Level
2.2L Eng,Normally Aspirated2.81.5B
2.2L Eng,Turbocharger3.52.0B
Combination Procedure: STARTER FIELD COILS: Remove, Install, and Overhaul:
0.5B