FixVault

Load Floor: Installation

WARNING: This page is about a different car, the 2004 Dodge Pickup and 2004 Dodge Cab & Chassis. However, it is still accessible from the selected car via links, so may be relevant.
  1. Install the load floor and install the bolts.
  2. Tighten the bolts to 40 N.m (30 ft. lbs.).
  3. Fold the load floor down and install the nuts.
  4. Tighten the nuts to 25 N.m (18 ft. lbs.).
    Fig 1: Installing Rear Load Floor - Rear Fasteners
    G03563779Courtesy of DAIMLERCHRYSLER CORP.
    Fig 2: Installing Rear Load Floor - Typical
    G03563780Courtesy of DAIMLERCHRYSLER CORP.