FixVault

Installation - PDC Assembly

Fig 1: Power Distribution Center, Power Feed Connections & Bolts
GC0159190Courtesy of CHRYSLER GROUP, LLC
  1. Position the upper PDC component to the PDC base (3) in the engine compartment.
  2. Connect the three bulkhead connectors (2) located in the base of the PDC to the upper PDC component.
    Fig 2: Identifying Power Distribution Center, Power Feed Connections & Bolts
    GC0159652Courtesy of CHRYSLER GROUP, LLC
  3. Tighten three bolts (2) through the upper PDC component top until secure. Be sure to not over tighten and crack the base or upper tray.
  4. Connect all power feeds to their PDC posts.
  5. Install the PDC enclosure cover onto the assembled PDC assembly.
  6. Connect the negative battery cable to the negative battery post.