FixVault

Repair Procedures: Installation

  1. Install in the reverse order of removal.

    Battery (-) Terminal Tightening Nut: 

    4.0 ~ 6.0 N.m (0.4 ~ 0.6 kgf.m, 3.0 ~ 4.4 lb-ft)

    Battery (+) Terminal Tightening Nut:  7.8 ~ 9.8 N.m (0.8 ~ 1.0 kgf.m, 5.8 ~ 7.2 lb-ft)

    Battery Mounting Bracket And The Insulation Pad Installation  :

    9.8 ~ 14.7 N.m (1.0 ~ 1.5 kgf.m, 7.2 ~ 10.9 Ib-ft)

    Battery Tray Mounting Bolts:  9.8 ~ 14.7 N.m (1.0 ~ 1.5 kgf.m, 7.2 ~ 10.9 Ib-ft)

    NOTE:
    • When installing the battery, fix the mounting bracket on the tray correctly.