Battery Blower: Installation
- INSTALL NO. 1 HV BATTERY INTAKE DUCT
- Install the No 1 HV battery intake duct to the battery cooling blower assembly.
- INSTALL BATTERY COOLING BLOWER ASSEMBLY
- Install the battery cooling blower assembly with the 3 nuts and clip.
Torque: 8.0 N*m (82 kgf*cm, 71 in.*lbf)
- Install the 2 connectors to the battery cooling blower assembly
- Install the battery cooling blower assembly with the 3 nuts and clip.
- INSTALL NO. 2 HV BATTERY INTAKE DUCT
- Install the No 2 HV battery intake duct.
- INSTALL NO. 3 HV BATTERY INTAKE DUCT
- Install the No 3 HV battery intake duct with the clip.
- INSTALL LUGGAGE COMPARTMENT TRIM COVER ASSEMBLY RH (See INSTALLATION )
- INSTALL REAR FLOOR FINISH PLATE (See INSTALLATION )
- INSTALL FRONT LUGGAGE COMPARTMENT TRIM COVER (See INSTALLATION )
- INSTALL NO. 1 LUGGAGE COMPARTMENT LIGHT ASSEMBLY (See INSTALLATION )
- INSTALL DECK TRIM SIDE BOARD RH (See INSTALLATION )
- INSTALL ROPE HOOK ASSEMBLY (See INSTALLATION )
- INSTALL ROPE HOOK (See INSTALLATION )
- INSTALL NO. 1 COOLER COVER (w/ Rear Cooler) (See INSTALLATION )
- INSTALL LUGGAGE COMPARTMENT MAT SUB-ASSEMBLY (See INSTALLATION )