FixVault

Front Stabilizer Control Link Inspection

  1. Remove the stabilizer control link from the vehicle. (See FRONT STABILIZER REMOVAL/INSTALLATION .)
  2. Inspect for bending or damage. If there is any malfunction, replace the stabilizer control link.
  3. Rotate the ball joint stud 10 times  and shake it side to side 10 times  .
  4. Measure the ball-joint rotational torque using an Allen wrench and a torque wrench.
    Fig 1: Measuring Ball-Joint Rotational Torque Using Allen Wrench And Torque Wrench
    G08150427

    Front stabilizer control link ball joint rotational torque 

    • 0.2-2.6 N.m {2.1-26 kgf.cm, 1.8-23 in.lbf}
    • If not within the specification, replace the stabilizer control link.