FixVault

PID/Data Monitor Inspection

  1. Connect the M-MDS to the DLC-2.
  2. Switch the ignition ON (engine off).
  3. Display PID EGRP_ACT and simulation item SEGRP_DSD using the M-MDS. (See PCM INSPECTION .)
  4. Verify that the PID EGRP_ACT value conforms to the simulation item SEGRP_DSD value when the EGR valve opening angle (simulation item: SEGRP_DSD) is driven using the simulation function.
    • If it cannot be verified, perform the voltage inspection. (See VOLTAGE INSPECTION .)
      G15654583Courtesy of MAZDA MOTORS CORP.