Component Inspection
- CHECK EXHAUST VALVE TIMING (EVT) CONTROL SOLENOID VALVE-1
- Turn ignition switch OFF.
- Disconnect EVT control solenoid valve harness connector.
- Check the resistance between EVT control solenoid valve terminals as per the following.
EVT control solenoid valve Condition Resistance Terminal 1 2 Temperature 20°C (68°F) 6.7 - 7.7 Ω - Check the resistance between EVT control solenoid valve terminal and solenoid valve body.
EVT control solenoid valve - Resistance Terminal 1 Solenoid valve body Not existed 2
Is the inspection result normal?
>>
GO TO 2.
>>
Replace EVT control solenoid valve. Refer to Exploded View .
- CHECK EVT CONTROL SOLENOID VALVE-2
- Remove EVT control solenoid valve. Refer to Exploded View .
- Provide battery voltage between EVT control solenoid valve terminals 1 and 2, and then interrupt it. Check that the plunger moves as shown in the figure, below.CAUTION:
Do not apply battery voltage continuously for 5 seconds or more. Doing so may result in damage to the coil in EVT control solenoid valve.
NOTE:Always replace O-ring when EVT control solenoid valve is removed.
Is the inspection result normal?
>>
INSPECTION END
>>
Replace EVT control solenoid valve. Refer to Exploded View .