Test Description
WARNING: This page is about a different car, the 2007 Saturn Vue. However, it is still accessible from the selected car via links, so may be relevant.
The numbers below refer to the step numbers on the diagnostic table.
- 2: Listen for an audible click when the headlamp relay operates. Command both the ON and OFF states. Repeat the commands, as necessary.
- 3: Tests for voltage at the coil side of the headlamp relay. The BACKUP/TURN fuse supplies battery positive voltage to the coil side of the headlamp relay.
- 4: Verifies that the BCM is providing ground to the headlamp relay.
DTC B2575
| Step | Action | Yes | No |
|---|---|---|---|
| Schematic Reference: Headlights/Daytime Running Lights (DRL) Schematics | |||
| 1 | Did you perform the Diagnostic System Check - Vehicle? | Go to Step 2 | Go to Diagnostic System Check - Vehicle |
| 2 |
|
Go to Testing for Intermittent Conditions and Poor Connections | Go to Step 3 |
| 3 |
|
Go to Step 4 | Go to Step 8 |
| 4 |
|
Go to Step 6 | Go to Step 5 |
| 5 | Test the control circuit of the headlamp relay for a high resistance or an open. Refer to Circuit Testing
and Wiring Repairs
. Did you find and correct the condition? |
Go to Step 11 | Go to Step 7 |
| 6 | Inspect for poor connections at the headlamp relay. Refer to Testing for Intermittent Conditions and Poor Connections
and Connector Repairs
. Did you find and correct the condition? |
Go to Step 11 | Go to Step 9 |
| 7 | Inspect for poor connections at the harness connector of the body control module (BCM). Refer to Testing for Intermittent Conditions and Poor Connections
and Connector Repairs
. Did you find and correct the condition? |
Go to Step 11 | Go to Step 10 |
| 8 | Repair the open in the coil side battery positive voltage circuit of the headlamp relay. Refer to Wiring Repairs
. Did you complete the repair? |
Go to Step 11 | - |
| 9 | Replace the headlamp relay. Refer to Relay Replacement (Attached to Wire Harness)
or Relay Replacement (Within an Electrical Center)
. Did you complete the replacement? |
Go to Step 11 | - |
| 10 | Replace the BCM. Refer to Control Module References
for replacement, setup, and programming. Did you complete the replacement? |
Go to Step 11 | - |
| 11 |
|
Go to Step 2 | System OK |