Installation Procedure

  1. Install the shift control closeout boot (1).
  2. Push the shift control closeout boot (1) down until it seats on the control.
    Fig 1: Pushing Shift Control Closeout Boot
    G01766680Courtesy of GENERAL MOTORS CORP.
    NOTE: Use the correct fastener in the correct location. Replacement fasteners must be the correct part number for that application. Fasteners requiring replacement or fasteners requiring the use of thread locking compound or sealant are identified in the service procedure. Do not use paints, lubricants, or corrosion inhibitors on fasteners or fastener joint surfaces unless specified. These coatings affect fastener torque and joint clamping force and may damage the fastener. Use the correct tightening sequence and specifications when installing fasteners in order to avoid damage to parts and systems.
  3. Install the shift control closeout boot bolts (1).

    Tighten 

    Tighten the shift control closeout boot bolts (1) to 2 N.m (18 in lbs).

  4. Install the control lever handle. Refer to Control Lever Handle Assembly Replacement .
    Fig 2: Installing Shift Control Closeout Boot Bolts
    G01766681Courtesy of GENERAL MOTORS CORP.