Installation Procedure
- Install the front transaxle mounting bracket on the transaxle assembly.
Tighten: Tighten the bolt to 64 N.m (47 lb ft).
- Install the left transaxle mounting bracket on the transaxle assembly.
Tighten: Tighten the bolt to 52 N.m (38 lb ft).
- Position the transaxle on the front suspension crossmember.
- Install the 6 transaxle to engine retaining bolts.
Tighten:
- Tighten the bolts (1) to 64 N.m (47 lb ft).
- Tighten the bolt (2) to 46 N.m (35 lb ft).
- Tighten the bolts (3) to 23 N.m (17 lb ft).
- Install the front mount through bolt.
Tighten: Tighten the bolt to 52 N.m (38 lb ft).
- Install the transfer case assembly on the transaxle. Refer to Transfer Case Replacement in Transfer Case - Vibe.
- Connect the 3 electrical connectors to the transaxle.
- Install the 2 bolts and ground cables to the transaxle.
Tighten: Tighten the bolts to 10 N.m (7 lb ft).
- Install the engine and transaxle as an assembly in the vehicle. Refer to Engine Replacement in Engine Mechanical - 1.6L (LV6).
- Install the 6 torque converter bolts.
Tighten: Tighten the bolts to 28 N.m (20 lb ft).
- Install the starter assembly in the vehicle. Refer to Starter Motor Replacement in Engine Electrical.
- Install the flywheel inspection cover
- Install the drain plug with a new gasket.
Tighten: Tighten the drain plug to 49 N.m (36 lb ft).
- Lower the vehicle.
- Fill the transaxle with 2.9 L (3.06 qt) of T-IV (GM Part No. 88900925).
NOTE:
Refer to Fastener Notice
in Cautions and Notices.
IMPORTANT:
The anodized (gold colored) bolt must be installed first. This bolt is to insure proper alignment for the other 5 bolts.