  1. Set the select lever in "N" position.
  2. Install the control valve and ground earth connectors.
    1. Tightening torque:  8 N.m (0.8 kgf-m, 5.8 ft-lb)
      Fig 1: Installing Control Valve
      G02960463Courtesy of SUBARU OF AMERICA, INC.
  3. Connect all connector.
    Fig 2: Connecting All Connectors
    G02960464Courtesy of SUBARU OF AMERICA, INC.
  4. Attach the magnet at the specified position.
    Fig 3: Attaching Magnet
    G02960465Courtesy of SUBARU OF AMERICA, INC.
  5. Apply proper amount of liquid gasket to the entire oil pan mating surface.
    1. Fluid packing:  THREE BOND 1217B
    Fig 4: Applying Proper Amount Of Liquid Gasket To Entire Oil Pan Mating Surface
    G02960466Courtesy of SUBARU OF AMERICA, INC.
  6. Apply liquid gasket fully to 3 holes other than screw holes on the transmission case.
    1. Fluid packing:  THREE BOND 1217B
    Fig 5: Applying Liquid Gasket Fully To Three Holes
    G02960467Courtesy of SUBARU OF AMERICA, INC.
  7. Install the oil pan.
    NOTE: Uniformly tighten the bolts in several passes.
    1. Tightening torque:  4.9 N.m (0.5 kgf-m, 3.6 ft-lb)
  8. Pour ATF into the oil charge pipe.
    1. Recommended fluid:  Dexron III type automatic transmission fluid
    2. Fluid capacity:  9.3 - 9.6 (9.8 - 10.1 US qt, 8.2 - 8.4 Imp qt)
  9. Check the level of the ATF.