Starting/Charging (H4SO): Generator: Inspection: Stator

  1. Continuity test

    Inspect the continuity between the stator coil lead wire terminals. If the resistance is 1 MΩ or more, replace the stator assembly because the lead wire is damaged.

    Fig 1: Checking Continuity Between Stator Coil Lead Wire Terminals
    G04992988
  2. Insulation test

    Inspect the continuity between the stator coil stator core and lead wire terminals. If the resistance is 1Ω or less, replace the stator assembly because the stator coil is grounded.

    Fig 2: Checking Continuity Between Stator Coil Stator Core And Lead Wire Terminals
    G04997985