Intake Manifold: Assembly

NOTE: When assembling the nipple, apply liquid gasket.

Liquid gasket: 

THREE BOND 1105 (Part No. 004403010) or equivalent 

Tightening torque: 

17 N.m (1.7 kgf-m, 12.5 ft-lb) 

  1. Secure the fuel pipe to intake manifold with bolts.

    Tightening torque: 

    6.4 N.m (0.7 kgf-m, 4.7 ft-lb) 

    Fig 1: Locating Bolts Which Hold Fuel Pipe Onto Intake Manifold
    G07662724Courtesy of SUBARU OF AMERICA, INC.
  2. Connect the fuel pipe LH to the fuel pipe.
    NOTE: Connect the quick connector securely.
    Fig 2: Identifying Quick Connector Which Hold Fuel Injector Pipe LH To Fuel Pipe
    G07662725Courtesy of SUBARU OF AMERICA, INC.
  3. Connect the fuel pipe RH to the fuel pipe.
    NOTE: Connect the quick connector securely.
    Fig 3: Identifying Quick Connector Which Hold Fuel Injector Pipe RH To Fuel Pipe
    G07662726Courtesy of SUBARU OF AMERICA, INC.
  4. Install the fuel injector.
    NOTE: Use new O-rings.
  5. Secure the fuel injector pipe to intake manifold with bolts.
    • RH side

      Tightening torque: 

      19 N.m (1.9 kgf-m, 14.0 ft-lb) 

      Fig 4: Locating Bolts Which Hold Fuel Injector Pipe Onto Intake Manifold - RH Side
      G07662727Courtesy of SUBARU OF AMERICA, INC.
    • LH side

      Tightening torque: 

      19 N.m (1.9 kgf-m, 14.0 ft-lb) 

      Fig 5: Locating Bolts Which Hold Fuel Injector Pipe On Intake Manifold - LH Side
      G07662728Courtesy of SUBARU OF AMERICA, INC.

      Tightening torque: 

      6.4 N.m (0.7 kgf-m, 4.7 ft-lb) 

      Fig 6: Locating Bolts Which Hold Fuel Injector Pipe On Intake Manifold - LH Side
      G07662729Courtesy of SUBARU OF AMERICA, INC.
  6. Install the engine harness to the intake manifold.
  7. Secure the engine harness to intake manifold with bolts.

    Tightening torque: 

    19 N.m (1.9 kgf-m, 14.0 ft-lb) 

    Fig 7: Locating Bolts Holding Engine Harness To Intake Manifold
    G07662730Courtesy of SUBARU OF AMERICA, INC.
  8. Install the purge control solenoid valve. < Ref. to INSTALLATION , Purge Control Solenoid Valve. >
  9. Connect the connectors (A) to fuel injector.
  10. Hold the engine harness to fuel injector pipe by harness band (B).
    Fig 8: Identifying Harness Band Which Holds Engine Harness To Fuel Injector Pipe And Fuel Injector Connectors
    G07662731Courtesy of SUBARU OF AMERICA, INC.
  11. Install the fuel pipe protector RH.

    Tightening torque: 

    19 N.m (1.9 kgf-m, 14.0 ft-lb) 

    Fig 9: Locating Fuel Pipe Protector Bolts - RH
    G07662732Courtesy of SUBARU OF AMERICA, INC.
  12. Install the fuel pipe protector LH.

    Tightening torque: 

    19 N.m (1.9 kgf-m, 14.0 ft-lb) 

    Fig 10: Locating Fuel Pipe Protector Bolts - LH
    G07662733Courtesy of SUBARU OF AMERICA, INC.
  13. Install the plug cord stay.

    Tightening torque: 

    6.4 N.m (0.7 kgf-m, 4.7 ft-lb) 

    Fig 11: Locating Plug Cord Stay
    G07662734Courtesy of SUBARU OF AMERICA, INC.
  14. Install the EGR valve. < Ref. to INSTALLATION , EGR Valve. >
  15. Install the throttle body to the intake manifold. < Ref. to INSTALLATION , Throttle Body. >
  16. Install the ignition coil and ignitor assembly. < Ref. to INSTALLATION , Ignition Coil and Ignitor Assembly. >
  17. Install the engine ground terminal to intake manifold.

    Tightening torque: 

    19 N.m (1.9 kgf-m, 14.0 ft-lb) 

    Fig 12: Locating Engine Ground Terminal At Intake Manifold
    G07662735Courtesy of SUBARU OF AMERICA, INC.