FixVault

Starting System & Charging System: Starter: Installation

  1. Install the starter and cable stay.
    NOTE: For the MT model, a bolt is used in the lower side of the starter.

    Tightening torque: 

    50 N.m (5.1 kgf-m, 36.9 ft-lb)

  2. Connect the connector, terminal B and ground terminal.

    Tightening torque: 

    Terminal B 

    11 N.m (1.1 kgf-m, 8.1 ft-lb)

    Ground terminal 

    14 N.m (1.4 kgf-m, 10.3 ft-lb)

  3. Install the front wheel LH. Ref. to WHEEL AND TIRE SYSTEM>Tire and Wheel>INSTALLATION .
  4. Install the air intake boot. Ref. to INTAKE (INDUCTION) (H4DO)>Air Intake Boot>INSTALLATION .
  5. Connect the battery ground terminal. Ref. to REPAIR CONTENTS>NOTE>BATTERY .