  1. INSTALL COMBINATION METER ASSEMBLY 
    1. Connect the connectors.
    2. Install the combination meter assembly with the 4 screws.
      Fig 1: Identifying Combination Meter Assembly With Screws
      G05140997Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  2. INSTALL INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY 
    1. Install the instrument cluster finish panel sub-assembly with the 4 clips.
  3. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL 
  4. PERFORM INITIALIZATION 
    1. Perform initialization.
      NOTE: Some systems need initialization when disconnecting the cable from the negative battery terminal.