FixVault

Transmission Control Cable: Installation

  1. INSTALL TRANSMISSION CONTROL CABLE ASSEMBLY 
    1. Install the No. 2 shift cable grommet retainer to the transmission control cable assembly.
      Fig 1: Installing No. 2 Shift Cable Grommet Retainer To Transmission Control Cable Assembly
      G04977189Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    2. Install the control cable assembly through the floor hole.
    3. Install the control cable assembly with the 2 bolts.

      Torque: 5.0 N*m (51 kgf*cm, 44 in.*lbf) 

    4. Connect the ends of the 2 cables and install the 2 washers and 2 clips.
      Fig 2: Locating Control Cable Bracket Clips
      G04974159Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    5. Install 2 new clips to the control cable bracket.
  2. INSTALL TRANSMISSION CONTROL CABLE ASSEMBLY 
    1. Connect the control cable to the shift lever retainer.
      Fig 3: Identifying Cable Outer Lock
      G04977182Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
      NOTE:
      • The projecting part of the cable outer should face upward when the shift cable is connected.
      • After installation, make sure that the cable outer lock is projecting from A as shown in the illustration.
    2. Connect the end of the shift cable to the shift lever assembly with the clip.
      Fig 4: Connecting End Of Select Cable To Shift Lever Assembly With Clip
      G04977183Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    3. Connect the end of the select cable to the shift lever assembly with a new clip.
      NOTE:
      • The serrated part of the select cable point should face upward when the select cable point is connected.
      • The clip should be installed in the direction as shown in the illustration.
  3. INSTALL CENTER AIRBAG SENSOR ASSEMBLY  (See INSTALLATION )
  4. INSTALL AIR CONDITIONER UNIT ASSEMBLY 

    See INSTALLATION .

  5. INSTALL INSTRUMENT PANEL SAFETY PAD SUB-ASSEMBLY 

    See INSTALLATION .

  6. INSTALL UPPER CONSOLE REAR PANEL SUB-ASSEMBLY  (See INSTALLATION )
  7. INSTALL UPPER CONSOLE PANEL  (See INSTALLATION )
  8. INSTALL NO. 2 INSTRUMENT CLUSTER FINISH PANEL GARNISH  (See INSTALLATION )
  9. INSTALL NO. 1 INSTRUMENT CLUSTER FINISH PANEL GARNISH  (See INSTALLATION )
  10. INSTALL SHIFT LEVER KNOB SUB-ASSEMBLY  (See INSTALLATION )
  11. INSTALL BATTERY  (See INSTALLATION )
  12. INSTALL AIR CLEANER CASE SUB-ASSEMBLY  (See INSTALLATION )
  13. INSTALL AIR CLEANER CAP SUB-ASSEMBLY  (See INSTALLATION )
  14. INSTALL AIR CLEANER INLET ASSEMBLY  (See INSTALLATION )
  15. INSTALL NO. 1 ENGINE COVER SUB-ASSEMBLY  (See INSTALLATION )
  16. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL  (See INSTALLATION )