FixVault

Throttle Body: Installation

  1. INSTALL THROTTLE WITH MOTOR BODY ASSEMBLY 
    1. Install a new gasket and the throttle with motor body with the 4 bolts.

      Torque: 11 N*m (112 kgf*cm, 9 ft.*lbf) 

      Fig 1: Identifying Throttle With Motor Body Bolts
      G05553858Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    2. Connect the throttle motor connector.
    3. Connect the water by-pass hose No. 4.
      Fig 2: Identifying Water By-Pass Hose No 4
      G05553859Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    4. Connect the water by-pass hose No. 5.
      Fig 3: Identifying Water By-Pass Hose No 5
      G05553860Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  2. INSTALL AIR CLEANER ASSEMBLY 
    1. Install the air cleaner with the 2 bolts.

      Torque: 8.0 N*m (82 kgf*cm, 71 in.*lbf) 

      Fig 4: Identifying Hose Clamps & Air Cleaner Bolts
      G05553861Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    2. Tighten the 2 hose clamps.
    3. Install the 2 wire harness clamps.
    4. Connect the mass air flow meter connector.
    5. Connect the vacuum hose.
      Fig 5: Identifying Mass Air Flow Meter Connector & Wire Harness Clamps
      G05553862Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
    6. Connect the ventilation hose No. 2.
      Fig 6: Identifying Ventilation Hose No. 2
      G05553863Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002
  3. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL 

    Torque: 3.9 N*m (40 kgf*cm, 35 in.*lbf) 

  4. ADD ENGINE COOLANT  (See REPLACEMENT )
  5. CHECK FOR ENGINE COOLANT LEAKAGE  (See REPLACEMENT )
  6. INSTALL V-BANK COVER 
    1. Install the V-bank cover with the 2 nuts.

      Torque: 7.5 N*m (76 kgf*cm, 66 in.*lbf) 

      Fig 7: Identifying V-Bank Cover Nuts
      G05553864Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002