FixVault

Shift Lever: Installation: Installation

  1. INSTALL SHIFT LOCK CONTROL UNIT ASSEMBLY 
    1. Install the shift lock control unit assembly with the 3 nuts.
      Fig 1: Identifying Shift Lock Control Unit Assembly, Connector & Nuts
      GTY227317Courtesy of © TOYOTA, LICENSE AGREEMENT TMS1002

      Torque: 12 N*m (122 kgf*cm, 9 ft.*lbf) 

    2. Connect the connector to the shift lock control unit assembly.
  2. INSTALL LOWER CENTER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY  . Refer to INSTALLATION - Step 30
  3. INSTALL INTEGRATION CONTROL AND PANEL ASSEMBLY  . Refer to INSTALLATION - Step 31
  4. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL 
    NOTE:

    When disconnecting the cable, some systems need to be initialized after the cable is reconnected. Refer to INITIALIZATION .

  5. INSTALL REAR NO. 3 FLOOR BOARD  . Refer to INSTALLATION - Step 58
  6. INSTALL REAR DECK FLOOR BOX  . Refer to INSTALLATION - Step 59
  7. INSTALL REAR NO. 2 FLOOR BOARD (for Separate Type)  . Refer to INSTALLATION - Step 60
  8. INSPECT SHIFT LEVER 
    1. Turn the power switch on (IG).
    2. Check that all available shift positions can be selected moving the shift lever.

      HINT: 

      After the shift lever is replaced with a new one, perform the above operation. If this operation is not performed, moving the shift lever may not initially select shift positions.