FixVault

Installation [08/2019 - ]: Procedure

  1. INSTALL POWER SWITCH 
    1. Engage the 2 claws to install the power switch.
  2. INSTALL CENTER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY WITH NAVIGATION RECEIVER ASSEMBLY (w/ Navigation System) 

    Refer to PROCEDURE - Step 16

  3. INSTALL CENTER INSTRUMENT CLUSTER FINISH PANEL UPPER (w/ Navigation System) 

    Refer to PROCEDURE - Step 17

  4. INSTALL CENTER INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY (w/o Navigation System) 

    Refer to PROCEDURE - Step 15

  5. INSTALL INSTRUMENT PANEL FINISH PANEL END RH 

    Refer to PROCEDURE - Step 18